Part 15 limits check

Field strength, power and antenna limits for unlicensed AM and FM, and a quick check of your transmitter.

FM: 250 microvolts per meter, measured at 3 meters

On FM (88-108 MHz), an unlicensed transmitter has to stay inside a 200 kHz channel, with field strength no greater than 250 µV/m (48 dBµV/m) at a distance of 3 meters (47 CFR 15.239). That works out to roughly 18.75 nanowatts radiated in free space.

AM: 100 milliwatts with a 3-meter antenna

On AM (510-1705 kHz), an unlicensed transmitter is limited to 100 mW of input to the final RF stage, and the antenna, ground lead and transmission line combined cannot exceed 3 meters (47 CFR 15.219). Anything emitted outside the AM band has to be attenuated by 20 dB or more.

More Part 15 choices for AM

  • Carrier current and leaky coax: on 525-1705 kHz, field strength is capped at 15 µV/m, taken from the cable or power line at a distance in meters of 47,715 / frequency-in-kHz (roughly 48 m at 1000 kHz). 47 CFR 15.221(a).
  • Campus AM: on its own campus, a school or college station has no field strength cap, provided the general limit is met at the campus boundary (24 µV/m at 30 m for 1000 kHz) and keeps out of the protected contours of licensed AM stations. 47 CFR 15.221(b), (d) and 15.209.

All the rules together

ServiceLimitRule
FM, 88-108 MHz250 µV/m at 3 m in a 200 kHz channel; the 15.209 general limits outside it15.239
AM, 510-1705 kHz100 mW input; 3 m line, antenna and ground lead15.219
AM carrier current15 µV/m at 47,715 / f(kHz) m15.221
EquipmentFCC-certified before it is sold (carrier current and campus AM: supplier's declaration)15.201
InterferenceNo harmful interference; stop if you cause it15.5

Need actual coverage?

With a licensed LPFM you reach a few miles instead of a few yards. Nexus Broadcast locates LPFM and translator channels and prepares the FCC applications.

Engineering for FCC filingsBrowse LPFM stations

Based on the FCC rules in the eCFR as of October 14, 2026. This is guidance, not legal advice. Not an FCC product.